This week, teams presented their first official presentations of the semester. Ours can be found in the below link. To summarize our progress so far, our 3D printing source failed to provide our print and had us find a new source of printing. This makes us about 2 weeks behind schedule and preventing us from making further modifications to accommodate for the controls and bogey team. Fortunately we still have enough time to make one more version before Maker Faire as intended. Right now the priority is to find another printing source that can be reliable.
https://docs.google.com/presentation/d/1guTPmBqMLvPL30xQpiMvD5ka80hHPlwlvpc35xBgSZ4/edit#slide=id.g3208203d60_0_237
Wednesday, February 21, 2018
Thursday, February 15, 2018
2/14 Meeting
This week the team finished up the model 3 and was able to procure a free 3D printing source which will be finished printing and sent to us by next Friday. Screenshots of the finished prototype can be found below. Also, the team has finished the first presentation of the semester and likely will be presenting next week.
Thursday, February 8, 2018
2/7 Meeting
This week's meeting was fairly short. During this meeting the team made finishing touches on the final draft of model 3. Below is the current state of the draft. Hollowing out the model and some aesthetic changes will be made as the week goes on. Also, a reliable printing source is still in the process in being found as Yousseffi has not gotten back to us and other services are charging more than we are willing to spend.
Subscribe to:
Posts (Atom)
Final Report and Work Summary
The following link redirects you to my team's final report on our project that discusses the overall project of what the SPARTAN Superwa...
-
Today, we found out the Viswanathan's printer won't be able to print our cabin due to the required print time. Luckily, we still ha...
-
No meeting today. Presentation in 189 However the Central Machine Shop was able to finish our second model print. Our third and final prin...
-
Since the successful completion of the first model, all there is left to do is to find a source to finish 2 more models for the track and ba...